mepco new connection

Mepco New Connection 2025

Getting a MEPCO new connection can often feel overwhelming for consumers who are not familiar with the process. Whether you are building a new house, opening a shop, or expanding your business, securing an electricity connection is the first step towards comfort and growth. Unfortunately, many applicants struggle with missing documents, confusing forms, and long waiting times. This guide provides a clear roadmap to apply for a new MEPCO connection, highlighting all requirements, official procedures, and expert tips to make the process faster and smoother.

If you already a MEPCO user and want to check your latest bill, click  MEPCO BILL ONLINE .

Understanding MEPCO’s Role in New Connections

The Multan Electric Power Company (MEPCO) supplies electricity to more than 13 districts in South Punjab. With millions of registered consumers, MEPCO manages not only bill distribution and maintenance but also the entire application system for new electricity connections.

A new connection request is not just about wiring—it is an official contract between the consumer and the power company. MEPCO ensures that every applicant provides verified documents, property proof, and a demand notice payment before installing the meter.

Step-by-Step Process for MEPCO New Connection

Applying for a new MEPCO electricity connection requires patience and accuracy. Below is a breakdown of the complete process:

1. Application Form Submission

  • Visit the official MEPCO office or the mepco new connection

  • Fill out all fields carefully, including property address, applicant CNIC, and contact details.

2. Required Documents

Attach the following documents with the application:

  • Copy of applicant’s CNIC

  • Proof of property ownership (registry, allotment letter, or rent agreement with NOC)

  • Attested copy of neighbor’s electricity bill (for reference)

  • Undertaking on stamp paper (as per MEPCO rules)

3. Demand Notice Issuance

Once the documents are verified, MEPCO issues a demand notice, which includes charges for meter installation, wiring, and service line.

4. Demand Notice Payment

  • Pay the demand notice at the designated bank branch.

  • Keep a copy of the paid challan as proof of payment.

  • If you need any assistance during the application process, visit  MEPCO HELPLINE for support.

5. Meter Installation

After payment confirmation, MEPCO dispatches a technical team for inspection and installation of the meter.
Check Your New / old MEPCO WAPDA Connection Bill Here

Timeframe for a New MEPCO Connection

On average, the process of acquiring a new MEPCO connection takes 30 to 45 days. However, delays can occur if:

  • Documents are incomplete or incorrect.

  • The applicant does not pay the demand notice on time.

  • There are technical issues in the local feeder or grid system.

Pro tip: Always follow up with the MEPCO office to avoid unnecessary waiting.

Commercial vs Domestic New Connections

Not all new connections are the same. MEPCO differentiates between domestic, commercial, and industrial connections.

  • Domestic Connection → For homes, apartments, and residential colonies.

  • Commercial Connection → For shops, plazas, and businesses with higher load requirements.

  • Industrial Connection → For factories and large-scale industries needing three-phase electricity.

Each category has a different fee structure, load assessment, and technical inspection. Consumers should clearly mention the connection type when applying.

Key Tips to Speed Up the Application

Applying for a MEPCO new connection can be smooth if you follow these insider tips:

  • Prepare all documents in advance to avoid rejection.

  • Use the official MEPCO online portal where possible, as it reduces paperwork.

  • Regularly follow up with the concerned SDO (Sub Divisional Officer).

  • Pay demand notice promptly to avoid delays in scheduling installation.

Conclusion – Secure Your MEPCO New Connection with Confidence

Applying for a MEPCO new connection is a straightforward process if handled correctly. By understanding the requirements, preparing documents in advance, and staying in contact with MEPCO staff, you can save both time and effort. Whether it’s for your home, shop, or factory, electricity is the backbone of modern life—and MEPCO ensures that every consumer gets connected securely and legally.

To calculate your bill amount befor time you can use our   MEPCO bill calculator
To check mepco peak hours details read our guide:  Mepco peak hourse

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *